Apply for a New LESCO Connection

To obtain a new electricity connection from LESCO (Lahore Electric Supply Company), follow these official steps:

  1. Collect the Application Form: Download the new connection form from the official LESCO website or visit the nearest customer service center.
  2. Fill in Required Details: Provide accurate information including applicant name, CNIC, address, load requirement, and type of connection.
  3. Attach Mandatory Documents:
    • Copy of CNIC
    • Proof of property ownership or rental agreement
    • No Objection Certificate (NOC) if applicable
    • Neighbor’s electricity bill copy for reference
  4. Submit the Application: Submit the form and documents to the relevant Sub-Divisional Office (SDO).
  5. Inspection & Demand Notice: After site inspection, LESCO issues a demand notice for connection charges.
  6. Payment & Meter Installation: Once the demand notice is paid, your connection will be installed within the prescribed timeframe.

For more info, visit: www.lesco.com.pk